Weekly report : from September 27 through October 03, 2001
Press release
October 04, 2001
UP2 plant :
At the UP2 plant, shearing of fuel assemblies from a batch of 900 MWe EDF fuel is in progress in the R1 head-end facility. A total of 482 metric tons of uranium have been processed to date this year. At the R7 vitrification facility, lines A and B are in service.
Line C is on standby. A total of 347 canisters of glass have been produced to date this year.
UP3 plant :
At the UP3 plant, shearing of fuel assemblies from BRUNSBUTTEL* is in progress in the T1 head-end facility. A total of 71 metric tons of uranium have been processed to date this year. At the T7 vitrification facility, line A is on standby. Lines B and C are in service. A total of 161 canisters of glass have been produced to date this year.
Works in the Moulinets cove :
The works of dismantling the old sea discharge pipe's, are keep going on. ISO 14001 : On October the 04th, Olivier PEYRAT, General Manager of AFAQ**, has officially delivered the ISO 14001 certification to the COGEMA La Hague plant.
This certification from an independent organism, show the goodwill of COGEMA to always respect the environment.
* German BWR Reactor.
** French Association for the Quality Insurance.

Report on diversity 2010
Field Report: Discover pragmatic examples of customer benefits
2007 figures: Economic, social, societal and environmental data
2006 figures: Economic, social, societal and environmental data
Rapport environnemental social et sociétal de COMURHEX Malvési 2010 [FR]
"Comurhex II" brochure
AREVA in India Press kit
"Georges Besse II" brochure
2010 Status of Safety at AREVA group facilities
Rapport de sûreté nucléaire et radioprotection 2009 du site du Tricastin