Weekly report : from September 06 through September 12, 2001
Press release
September 13, 2001
UP2 plant :
At the UP2 plant, shearing of fuel assemblies from a batch of 900 MWe EDF fuel is in progress in the R1 head-end facility.
A total of 413 metric tons of uranium have been processed to date this year.
At the R7 vitrification facility, lines A and B are in service. Line C is on standby.
A total of 308 canisters of glass have been produced to date this year.
UP3 plant :
At the UP3 plant, shearing of fuel elements from GOSGEN* is in progress in the T1 head-end facility.
A total of 52 metric tons of uranium have been processed to date this year.
At the T7 vitrification facility, lines A and C are on standby. Line B is in service.
A total of 146 canisters of glass have been produced to date this year.
Works in the Moulinets cove :
The works of laying out of building site in Anse des Moulinets zone, preceding the old sea discharge pipe's dismantling, are keep going on.
Dismantling of Point P (extremity of old pipe) is scheduled on September the 18th).
* Swiss PWR Reactor

Report on diversity 2010
Field Report: Discover pragmatic examples of customer benefits
2007 figures: Economic, social, societal and environmental data
2006 figures: Economic, social, societal and environmental data
Rapport environnemental social et sociétal de COMURHEX Malvési 2010 [FR]
"Comurhex II" brochure
AREVA in India Press kit
"Georges Besse II" brochure
2010 Status of Safety at AREVA group facilities
Rapport de sûreté nucléaire et radioprotection 2009 du site du Tricastin