Weekly report : from August 02 through 08, 2001
Press release
August 09, 2001
UP2 plant :
At the UP2 plant, R1 head-end facility is on shutdown period for maintenance.
A total of 332 metric tons of uranium have been processed to date this year.
At the R7 vitrification facility, lines A, B and C are on standby.
A total of 256 canisters of glass have been produced to date this year.
UP3 plant :
At the UP3 plant, T1 head-end facility is on a shutdown period for maintenance.
A total of 51 metric tons of uranium have been processed to date this year.
At the T7 vitrification facility, lines A, B and C are on standby.
A total of 146 canisters of glass have been produced to date this year.
On August the 14th, two empty casks having carried vitrified residues to Japan, will be unload at the Quai des Flamands.

Report on diversity 2010
Field Report: Discover pragmatic examples of customer benefits
2007 figures: Economic, social, societal and environmental data
2006 figures: Economic, social, societal and environmental data
Rapport environnemental social et sociétal de COMURHEX Malvési 2010 [FR]
"Comurhex II" brochure
AREVA in India Press kit
"Georges Besse II" brochure
2010 Status of Safety at AREVA group facilities
Rapport de sûreté nucléaire et radioprotection 2009 du site du Tricastin