From July 05 through July 11

Press release

July 12, 2001

 UP2 plant :

At the UP2 plant, R1 head-end facility is on shutdown period for maintenance.
A total of 332 metric tons of uranium have been processed to date this year.

At the R7 vitrification facility, lines B and C are in service, line A is on standby.
A total of 227 canisters of glass have been produced to date this year.

UP3 plant :

At the UP3 plant, T1 head-end facility is on a shutdown period for maintenance.
A total of 51 metric tons of uranium have been processed to date this year.

At the T7 vitrification facility, Line A is in service, lines B and C are on standby.
A total of 144 canisters of glass have been produced to date this year.