Weekly report : from April 19 through 25, 2001
Press release
April 26, 2001
UP2 plant :
At the UP2 plant, shearing of fuel assemblies from a batch of 1300 MWe EDF fuel is in progress in the R1 head-end facility.
A total of 124 metric tons of uranium have been processed to date this year.
At the R7 vitrification facility, line B is on standby, lines A and C are in service.
A total of 135 canisters of glass have been produced to date this year.
UP3 plant :
The head end plant is currently undergoing a scheduled shutdown. Maintenance operations are being carried out in accordance with the scheduled programme.
At the T7 vitrification facility, line B is in service, lines A and C are on standby.
A total of 92 canisters of glass have been produced to date this year.

Report on diversity 2010
Field Report: Discover pragmatic examples of customer benefits
2007 figures: Economic, social, societal and environmental data
2006 figures: Economic, social, societal and environmental data
Rapport environnemental social et sociétal de COMURHEX Malvési 2010 [FR]
"Comurhex II" brochure
AREVA in India Press kit
"Georges Besse II" brochure
2010 Status of Safety at AREVA group facilities
Rapport de sûreté nucléaire et radioprotection 2009 du site du Tricastin