Weekly report : from 29th March to 04th April, 2001
Press release
April 05, 2001
UP2 Plant :
The UP2 800 plant has been stopped except for the R7 vitrification facility.
Reminder : on the 24th February during a rincing operation, a leak was detected on the chute linking the shearing machine and the dissolver.
The repairing operation is in progress. The R1 facility should start again before April the 15th.
A total of 69 metric tons of uranium have been processed to date this year.
At the R7 vitrification facility, line B is on stand-by, lines A and C are in service.
A total of 99 canisters of glass have been produced to date this year.
UP3 Plant :
The head end plant is currently undergoing a scheduled shutdown. Maintenance operations are being carried out in accordance with the scheduled programme.
At the T7 vitrification facility, line B is in service, lines A and C are on stand-by.
A total of 74 canisters of glass have been produced to date this year.
Work in the Moulinets Cove :
The preparatory work for the dismantling of the former pipe is in progress. Interventions in the tidal range area are scheduled during low tides with a high coefficient from April 07 to 10, weather and sea conditions permitting.

Report on diversity 2010
Field Report: Discover pragmatic examples of customer benefits
2007 figures: Economic, social, societal and environmental data
2006 figures: Economic, social, societal and environmental data
Rapport environnemental social et sociétal de COMURHEX Malvési 2010 [FR]
"Comurhex II" brochure
AREVA in India Press kit
"Georges Besse II" brochure
2010 Status of Safety at AREVA group facilities
Rapport de sûreté nucléaire et radioprotection 2009 du site du Tricastin