Weekly report : from December 07 through 13, 2000

Press release

December 14, 2000

At the UP2 plant, shearing of fuel assemblies from a batch of 1300 MWe EDF fuel start again Wednesday the 13th of December, in the R1 head-end facility
A total of 761 metric tons of uranium have been processed to date this year.

At the R7 vitrification facility, lines A and B are in service, line C is on standby.
A total of 460 canisters of glass have been produced to date this year.

At the UP3 plant, the T1 head-end facility is on standby. Monitoring operations are in progress.
A total of 387 metric tons of uranium have been processed to date this year.

At the T7 vitrification facility, lines A, B and C are in service.
A total of 321 canisters of glass have been produced to date this year.