Weekly report : from December 07 through 13, 2000
Press release
December 14, 2000
At the UP2 plant, shearing of fuel assemblies from a batch of 1300 MWe EDF fuel start again Wednesday the 13th of December, in the R1 head-end facility
A total of 761 metric tons of uranium have been processed to date this year.
At the R7 vitrification facility, lines A and B are in service, line C is on standby.
A total of 460 canisters of glass have been produced to date this year.
At the UP3 plant, the T1 head-end facility is on standby. Monitoring operations are in progress.
A total of 387 metric tons of uranium have been processed to date this year.
At the T7 vitrification facility, lines A, B and C are in service.
A total of 321 canisters of glass have been produced to date this year.

Report on diversity 2010
Field Report: Discover pragmatic examples of customer benefits
2007 figures: Economic, social, societal and environmental data
2006 figures: Economic, social, societal and environmental data
Rapport environnemental social et sociétal de COMURHEX Malvési 2010 [FR]
"Comurhex II" brochure
AREVA in India Press kit
"Georges Besse II" brochure
2010 Status of Safety at AREVA group facilities
Rapport de sûreté nucléaire et radioprotection 2009 du site du Tricastin