At the UP2 plant, shearing of fuel assemblies from a batch of EDF 900 MWe fuel has been interrupted since February 13 in the R1 head-end facility. A total of 98 metric tons of uranium have been processed to date this year.
At the R7 vitrification facility, line A is in service. Lines B and C are on stand-by. A total of 54 canisters of glass have been produced to date this year.
At the UP3 plant, shearing of fuel elements from TIHANGE* were completed on 2/17 in the T1 head-end facility. Preparations for the shearing of fuel elements from BIBLIS** are in progress. A total of 11 metric tons of uranium have been processed to date this year.
At the T7 vitrification facility, lines A, B and C are on stand-by. A total of 40 canisters of glass have been produced to date this year.
Work in the Moulinets Cove
Work continues on modifications to the discharge pipe in the tidal basin:
- radiological monitoring of sediments has revealed no anomalies, although there are fluctuations close to the old discharge pipe;
- new sections of piping are ready to be submerged, pending favorable oceanic and meteorological conditions.
* Belgian PWR reactor
** German PWR reactor

Report on diversity 2010
Field Report: Discover pragmatic examples of customer benefits
2007 figures: Economic, social, societal and environmental data
2006 figures: Economic, social, societal and environmental data
Rapport environnemental social et sociétal de COMURHEX Malvési 2010 [FR]
"Comurhex II" brochure
AREVA in India Press kit
"Georges Besse II" brochure
2010 Status of Safety at AREVA group facilities
Rapport de sûreté nucléaire et radioprotection 2009 du site du Tricastin