Weekly report : from January 12 through January 18, 2000
Press release
January 21, 2000
At the UP2 plant, shearing of fuel assemblies from a batch of EDF 900 MWe fuel began on January 15 in the R1 head-end facility. A total of 11.5 metric tons of uranium have been processed to date this year.
At the R7 vitrification facility, all three lines are on stand-by.
At the UP3 plant, all units are shut down in the T1 head-end facility.
At the T7 vitrification facility, all three lines are on stand-by.
Work in the Moulinets Cove
Work continues on modifications to the discharge pipe in the tidal basin:
- radiological monitoring of sediments has revealed no anomalies, although there are fluctuations close to the old discharge pipe;
- underwater excavation of the center section was completed; the bottom of the basin was fitted (placement of ballast and backfilling)

Report on diversity 2010
Field Report: Discover pragmatic examples of customer benefits
2007 figures: Economic, social, societal and environmental data
2006 figures: Economic, social, societal and environmental data
Rapport environnemental social et sociétal de COMURHEX Malvési 2010 [FR]
"Comurhex II" brochure
AREVA in India Press kit
"Georges Besse II" brochure
2010 Status of Safety at AREVA group facilities
Rapport de sûreté nucléaire et radioprotection 2009 du site du Tricastin