Weekly report : from January 5 through January 12, 2000
Press release
January 14, 2000
At the UP2 plant, all units are shut down in the R1 head-end facility. Scheduled outage work is in progress.
At the R7 vitrification facility, all three lines are shut down.
At the UP3 plant, all units are shut down in the T1 head-end facility.
At the T7 vitrification facility, lines A and B are on stand-by; line C is in operation. A total of 3 canisters of glass have been produced to date this year.
Work in the Moulinets Cove
Work continues on modifications to the discharge pipe in the tidal basin:
- radiological monitoring of sediments has revealed no anomalies, although there are fluctuations close to the old discharge pipe;
- final excavation of the center section continued despite difficult oceanic and meteorological conditions.

Report on diversity 2010
Field Report: Discover pragmatic examples of customer benefits
2007 figures: Economic, social, societal and environmental data
2006 figures: Economic, social, societal and environmental data
Rapport environnemental social et sociétal de COMURHEX Malvési 2010 [FR]
"Comurhex II" brochure
AREVA in India Press kit
"Georges Besse II" brochure
2010 Status of Safety at AREVA group facilities
Rapport de sûreté nucléaire et radioprotection 2009 du site du Tricastin